  • 20 10 17 1 20_10_17_2 20 10 17 3 20 10 17 4 20 10 17 5    
  • 1st floor house / 4th floor;
  • Building 2-5 at home
  • Mounting the ceiling to 2-3 buildings
  • Delivery of water supply pipes;
  • Preparations for Terion Improvement
  • Delivery of roof mount materials;

  • Finishing the masonry on 1 house / 4 floors;
  • 3rd floor masonry / 2nd house;
  • Floor 2 / 3-4 brick;

  • Covering the 3rd floor of the first building
  • Overlapping 2 floors 2-3 houses;
  • Overlap 1 on the fourth building
  • Floor 5 building # 2;
  • Preliminary work on site improvement

  • Covering the third floor of 1 building
  • Covering the second floor of 2 buildings
  • 3-4 floor building

  • Floor 3 on the first house
  • Floor 2 masonry on the second to third; at home
  • Beginning of the 1st floor masonry on the fourth building
  • Concrete flooring at the fifth building
  • Works on water supply at 6-7 houses

  • Laying 3 at the front of the house
  • Floor 2 on second to third homes;
  • Construction of water supply pipes at the house of 4,5,6,7;
  • Completion of the 1st floor on the fifth building

  • Laying for 1,2,3,4,5 houses;
  • Freeze on 6.7 houses

  • Overlapping over 1,2,3 houses
  • Backfill on House 4
  • First floor bungalow;

  • Masonry of partitions on the second floor / first house;
  • 1st floor masonry at 2.3 building;
  • Concrete pouring into a building of 4.5

  • 2nd 1st / 2nd installment
  • pouring concrete, stairs and ground floor onto the 2nd house

  • Finishing the masonry on the second building / ground floor;
  • Ending the foundation, filling the ground with house 3
  • 4.5 Buildings for mounting formwork
  • 6.7 pit excavation house

  • Concrete pouring (first floor / first floor deck)
  • Laying the inner walls to the second building
  • Ending the installation of the foundation on the 3rd building;
  • Mounting the formwork at 4th building;
  • Concrete pouring on the 5th building, and mounting the second level of formwork;

  • Floor 1 of the first / second house
  • Foundation of foundation and mounting of formwork