As of 22.06.2021
- preparatory work for the overlap of the 4th floor in 7,8 houses;
- brick laying 3 floors in the 9th house;
- installation of internal gas supply networks in 1-6 houses;
- insulation 100 mm "Anserglob" 4-6 houses;
- preparatory work for the improvement of the territory.