As of 08/13/2021
- the laying of 7, 8, 9 houses was completed;
- brick laying at 10, 11 houses on the 1st floor;
- preparation for the installation of plastic windows in 7, 8, 9 houses;
- connection of internal gas supply networks in 1-6 houses;
- preparatory work for the improvement of the local area 1-6 houses;
- preparatory work for the arrangement of the roof in 7, 8, 9 houses.