As of April 11, 2022
- Insulation of facades of 7-11 buildings is 60%;
- Electrical wiring is installed from 7-10 houses at 100%, 11 houses are under construction;
- Plastering the walls of 7-10 houses is 100% complete, 11 houses are under construction;
- Installing plastic windows from 7-11 house to 100%;
- Installing armored doors from 7-9 houses at 100%;
- Planting and watering thuja from 1-6 house;
- Completed work on the installation of the roof of 7-11 houses at 100%.