As of 21.10.2022
- ✅ 80% of paving stones have been laid;
- ✅ The installation of tiles in the entrances is 85% completed;
- ✅ Completion of installation of internal gas supply networks;
- ✅ Installation of canopies for terraces is 90% completed.